Project Name
Kabita
Details

Kabita

Start
10/11/2016
End
27/12/2017
Word
১-৯
Project Type
kabita
Amount
৬৮৩০০০
label.Details.title

Kabita

Job description

The year 2016-2017 is the year-kabita

serial number


Source of allocation


Project name


Project details


The amount of money


Implementation rate

1


Kabita


Reclamation by Sandeep Dighipar road towards Misha Parisha -


Reclamation by Sandeep Dighipar road towards Misha Parisha -


1,40,000 / -


100%

2


Kabita


Setting up solar panels at Kashimila Mollapara Jami Mosque -


Setting up solar panels at Kashimila Mollapara Jami Mosque -




30,000 / -


100%

3


Kabita


Establishment of solar panel in East-Chhatni Fisheries Jeeb Mosque -


Establishment of solar panel in East-Chhatni Fisheries Jeeb Mosque -


30,000 / -


100%

4


Kabita


Setting up solar panels at Dakra Jami Mosque


Setting up solar panels at Dakra Jami Mosque




30,000 / -


100%

5


Kabita


Solar panels installed in Jahanabaj Wakyakyan;




Solar panels installed in Jahanabaj Wakyakyan;


30,000 / -


100%

6


Kabita


 Solar panels installed in Uqrail Akandpara Jami Mosque -


 Solar panels installed in Uqrail Akandpara Jami Mosque -




26,000 / -


100%




Total money








2,86,000 / -



The year 2017-2011 is the year-kabita

serial number


Source of allocation


Project name


Project details


The amount of money


Implementation rate

1


Kabita


Setting up solar panel in Uthrail big mosque.


Setting up solar panel in Uthrail big mosque.


33,000 / -


100%

2


Kabita


Installing solar panel in Uthrail-ul-VDP club.


Installing solar panel in Uthrail-ul-VDP club.


33,000 / -


100%

3


Kabita


Establishment of solar panels at Prasadkhali temple.


Establishment of solar panels at Prasadkhali temple.


33,000 / -


100%

4


Kabita


Setting up solar panels in Dumdama Social Work camp


Setting up solar panels in Dumdama Social Work camp


33,000 / -


100%

5


Kabita


Setting up solar panel in Santee Dighirpar Jame Mosque.


Setting up solar panel in Santee Dighirpar Jame Mosque.


33,000 / -


100%

6


Kabita


 Setting up the solar panel at the Sandhiya Kalitola temple.


 Setting up the solar panel at the Sandhiya Kalitola temple.


33,000 / -


100%

7


Kabita


Founding of solar panels in Sandra West Para Central Mosque.


Founding of solar panels in Sandra West Para Central Mosque.


33,000 / -


100%

8


Kabita


Establishment of solar panels at the mosque of East Chhatni Station Market.


Establishment of solar panels at the mosque of East Chhatni Station Market.


33,000 / -


100%

9


Kabita


Establishment of solar panel in East Chhatni Sardarpara Jami Mosque


Establishment of solar panel in East Chhatni Sardarpara Jami Mosque


33,000 / -


100%

10


Kabita


Setting up solar panels in the Hindu Chhatni Hindupara temple


Setting up solar panels in the Hindu Chhatni Hindupara temple


33,000 / -


100%

11


Kabita


Setting up solar panel in West Chattani Al Aqsa Jame Mosque


Setting up solar panel in West Chattani Al Aqsa Jame Mosque


34,000 / -


100%

12


Kabita


Setting up solar panels in West Chattani Jame Mosque


Setting up solar panels in West Chattani Jame Mosque


33,000 / -


100%










Total


3,97,000 / -



Md. Ershadul Haque (Tulu)

Chairman

Saftahara UP, Adamdighi, Bogra.